|
| |
Archived reports
May 11, 2006
- THE INTAKE STRUCTURE - LADWP Construction forces have poured 92’ of
concrete floor of the lined channel, and have poured 92’ of the 12’ 7” walls.
Concrete pours are scheduled to continue thru the month of June. The cut-off
wall behind the structure has been completed. Earth work is continuing in the
area where the rail car bridge will be placed. One footing for the bridge
abutments has been poured. The other footing for the bridge is formed and
scheduled to pour the week of May 15, 2006. The rail car bridge is scheduled
to be installed at the end of June. Radial gate operating winches have been
refurbished and installed in working order. Representatives from Portadam,
Inc. were on-site at the end of April to extend and reinforce the existing
coffer dam in the river channel. Currently the dam can safely accommodate
flows up to 700 cfs.
- CHANNEL CLEARING - The initial two miles of river channel have been
cleared. Temporary access roads have been lightly disced and seeded to
facilitate revegetation, taking advantage of recent rains. These roads are
closed to vehicular traffic.
- CHANNEL OBSTRUCTIONS - Five of the six channel obstructions scheduled to
be removed for the LORP have been completed. The bridge foundation south of
Mazourka Cyn Road is in the process of being modified.
- BLACKROCK WATERFOWL AREA- New berms have been been established in Thibaut
unit. Berms are in progress in Winterton and Blackrock units. Ditch work is
scheduled to begin by the end of May.
- MEASURING STATIONS - Construction began the first week of May for the
measuring station located north of Blackrock Ditch. Installation is scheduled
to be completed by May 19th.
- PUMP STATION -LADWP contractor Kiewit Pacific Co. has completed the slab
for the 50 cfs pump station sump floor. Approximately 95% of the walls have
been poured. Concrete work is scheduled to be completed on the walls by
mid-May. Excavation is complete for the air chamber and approximately 25% of
the protection slab and one of the three main slabs have been poured. The
permanent diversion structure earth work is complete. Sheet piling placement
is approximately 30% complete. Rip-rap and concrete placement for the
diversion structure has began. Excavation is complete for the permanent
settling basin. Armor rip-rap placement is scheduled for completion by the end
of May. Permanent service roads on the East and West sides are under
construction.
- BEAVER DAM REMOVALS - Area surveyed May 10, 2006. No action necessary at
this time.
April 14, 2006
- THE INTAKE STRUCTURE - LADWP Construction forces have poured 75’ of
concrete floor of the lined channel, and have poured 50’ of the 12’ 7” walls.
The next section of floor and walls are framed and scheduled to be poured on
Monday April 17, 2006. The footings for the cutoff wall behind the structure
are in place and the wall is formed and scheduled to be poured the week of
April 17, 2006. Earth work is continuing in the area where the rail car bridge
will be placed. Bridge abutments are being formed and are scheduled to be
poured the week of April 17, 2006. Radial gate operating winches have been
refurbished and are on-site and scheduled for installation the week of April
17, 2006. Representatives from Portadam, Inc. are scheduled to arrive by the
end of the month. LADWP crews will work with Portadam employees to extend and
reinforce the existing coffer dam in the river channel. Currently the dam can
safely accommodate 500 cfs and with reinforcement will be able to handle flows
up to 700 cfs.
- CHANNEL CLEARING - The initial two miles of river channel have been
cleared. Temporary access roads have been lightly disced and seeded to
facilitate revegetation, taking advantage of recent rains. These roads are
closed to vehicular traffic.
- CHANNEL OBSTRUCTIONS - April 5, 2006 LADWP construction crews began
removing the bridge berm and culverts near Blackrock Ditch Return. Work at
this site was completed on April 12, 2006.
- April 12, 2006 LADWP construction crews began removing the Eastside
canal diversion dam. Work was completed April 13, 2006.
- April 11, 2006 work began at Five Culverts. Work is scheduled for
completion the week of April 17, 2006.
- BLACKROCK WATERFOWL AREA - Work began on the Winterton and Waggoner Units
this week. Access roads are being graded and ditch and berm work are underway.
- PUMP STATION- LADWP contractor Kiewit Pacific Co. has completed the slab
for the 50 cfs pump station sump floor. Approximately 10% of the walls have
been poured. Concrete work is scheduled to continue on the walls for the next
couple of weeks. Excavation is complete for the air chamber and approximately
25% of the protection slab has been poured. The permanent diversion structure
has been excavated down to sub-grade and 80% of the backfill has been placed.
Sheet piling placement is approximately 5% complete. Rip-rap and concrete
placement for the diversion structure is scheduled for May. Excavation is
complete for the permanent settling basin. Armor rip-rap is scheduled for
installation. Permanent service roads on the East and West sides are being
compacted.
- BEAVER DAM REMOVALS - Area surveyed April12, 2006. No action necessary at
this time.
March 29, 2006
- THE INTAKE STRUCTURE - LADWP Construction forces have poured 50’ of
concrete floor of the concrete lined channel, and have formed 50’ of the
walls. Approximately 25’ of wall will be poured later this week. The slide
gate has been installed on the face of the intake structure and all three
radial gates have been installed. Excavation has begun for the bridge
abutments and for the Langemann gate.
- CHANNEL CLEARING - Initial channel clearing activities were completed
today. Approximately the first two-miles of river channel were cleared to
accommodate the 40 cfs flows. Abandoned access roads are being lightly disced
and seeded to facilitate revegetation, taking advantage of recent rains. These
roads are being closed to vehicular traffic.
- BLACKROCK WATERFOWL AREA - Materials are on order and initial survey work
and planning are complete.
- PUMP STATION - LADWP contractor Kiewit Pacific Co. has poured
approximately 75% of the slab for the 50 cfs pump station. Slab is scheduled
for completion this week. The air chamber location is being excavated. The
permanent diversion structure has been excavated down to subgrade and
construction activities will continue as scheduled. Excavation continues at
the permanent settling basin as well as construction of the permanent East
Side Service Road.
- BEAVER DAM REMOVALS - Approximately 4 Beaver dams were removed in the
Lower Owens River Delta March 16th and 17th. A LADWP helicopter equipped with
a grabber device worked to remove the dams. By removing these dams water
levels at the construction site are lowered. LADWP Watershed Resources staff
are monitoring the area for further beaver activity. If needed future dam
removal operations will be scheduled.
March 13, 2006
- THE INTAKE STRUCTURE Work is continuing around the Intake Structure where
the LA Aqueduct takes off from the Owens River at the beginning of the LORP's
62 mile Owens River Channel. LADWP construction crews have placed and slurried
95% of the rip rap required on the front of the Intake Structure.
Approximately 25’ of concrete floor has been poured of the concrete lined
channel. The temporary cofferdam was completed January 14, 2006, diverting the
Owens River flow away from the spillgates. The cofferdam will be removed after
construction of the spillgate is completed.
- CHANNEL CLEARING A little over 1 mile of river channel has been cleared by
LADWP construction crews. A prescribed burn is scheduled for the week of March
13, 2006 to help reduce the amount of biomass that must be removed from the
channel. 95% of abandoned access roads have been closed to vehicular access,
and lightly disced and seeded to facilitate revegetation.
- BLACKROCK WATERFOWL AREA Work is scheduled to begin the week of March 20,
2006.
- PUMP STATION LADWP contractor Kiewit Pacific Co. has cleared the project
area, diverted the flows of the Lower Owens around their work site, placed
temporary access roads across the river channel, performed a controlled burn
in conjunction with LADWP Resources staff to clear the work area in the river
channel and initiated construction dewatering activities. Raito, Inc., a
subcontractor to Kiewitt has completed deep foundation treatment in the pump
station footprint and for the air chamber. Settling basin and diversion dike
excavation and concrete placement for the pump station have began.
- BEAVER DAM REMOVALS Dam removals are scheduled for the week of March 13,
2006. A LADWP helicopter will remove the dams with ground assistance from
LADWP Resource staff and Construction crews. The dams marked for removal are
located in the area south of the river bridge adjacent to pump station.
March 8, 2006
- INTAKE STRUCTURE - Work is continuing at the Intake site, which marks the
start (north end) of the Lower Owens River Project. As of 3/8/06 a portion of
the concrete headwall where three rehabed radial gates will be located has
been poured. Forms and rebar for the first section of the spillbay are in
place, with concrete expected to be poured within the next few days. The crews
continue work on the spillbay. A temporary cofferdam is diverting the Owens
River flow away from the Intake structure; the cofferdam will be removed after
all construction in the area has completed.
- CHANNEL CLEARING - Channel clearing below the Intake is in progress,
presently focused on the upper section of the channel, with approximately
1,500 feet having been cleared as of 3/3/06.
- PUMPBACK STATION - As of 3/1/06 the bypass channel is in place, re-routing
the river's flow away from the construction site, and the dewatering process
has started with the installation of pumps and piping. Construction on the
actual pumpback station will begin after the completion of the dewatering
process.
| |
|