Recent Activity
Details of current and past work being accomplished as dictated
by the LORP work plan
February 2, 2007
(PHOTOS opens
in new window)
- BLACKROCK WATERFOWL AREA Construction crews are completing corridors and
ditches and testing the system.
- PUMP STATION - The contractor (Kiewit Pacific) is still on-site working
out the bugs in the system. Pumping capability has been attained.
- DEBRIS REMOVAL - LADWP construction crews, with assistance from CDF inmate
crews, are burning salt cedar slash piles.
- FENCING - Riparian fencing efforts are on-going.
- FLOWS - We are currently releasing 60 cfs from the Intake. LADWP
hydrographers are in the process of calibrating flow meters and establishing
reliable communications from remote measuring stations. Phase I flows have
been exceeded and we are working to stabilize the system to meet Phase II (baseflow)
obligations.
January 5, 2007 (PHOTOS opens in new window)
- BLACKROCK WATERFOWL AREA - Goose Lake and Twin Lake corridors are
complete. The final water control structures have been formed and are ready to
be poured next week.
- PUMP STATION - Pump tests are scheduled to begin this weekend.
- DEBRIS REMOVAL - Currently an LADWP helicopter is assisting with removal
of floating salt cedar slash and removal of other woody debris in the newly
wetted section of the river.
- FENCING - Fencing efforts are on-going. 17 miles of fencing has been
completed to date.
- FLOWS - We are currently releasing 18 cfs from the Intake. The entire
river system is wet and we are in the process of calibrating all riverine
measuring stations.
November 16, 2006 (PHOTOS opens in new window)
August 29, 2006 (PHOTOS opens in new window)
- THE INTAKE STRUCTURE The railcar bridge has been installed. The bridge
approaches will be complete by 9/2/2006. Additional concrete work is in
progress for the access ramp, and the pad for the flow velocity meter.
Scheduled work at the Intake is 97% complete with remaining work to be
completed by early November.
- CHANNEL CLEARING The initial two miles of river channel have been cleared.
- CHANNEL OBSTRUCTIONS Five of the six channel obstructions scheduled to be
removed for the LORP have been completed. The bridge foundation south of
Mazourka Cyn Road is in the process of being modified.
- BLACKROCK WATERFOWL AREA Designated work is 50% complete. Berm work is 80%
complete. Staff gages need to be placed, water control structures need to be
installed and some minor ditch work is scheduled.
- MEASURING STATIONS Blackrock, Georges and Reinhackle measuring stations
are complete with the exception of placement of electronics. Electronics will
be placed just prior to initial flows. Keeler Bridge measuring station is
approximately 60% complete. Work is scheduled for completion by mid-September.
The two temporary measuring stations in the delta will be installed late
September or early October.
- PUMP STATION LADWP contractor Kiewit Pacific Co. has completed 50% of the
concrete placement for the top deck of the pump station structure. The pump
station concrete work is approximately 90% complete. Progress continues on the
air chamber. 60% of the concrete has been placed. The 24’ diameter steel
sphere is scheduled for installation in early October. The customer station
was energized on 7/18/2006. Powerline installation for the pump station is
complete. The settling basin is complete. Permanent service roads on the East
and West sides are under construction and approximately 70% complete. The
Langemann gate has arrived and is scheduled for installation during September.
- BEAVER DAM REMOVALS No dam removals are scheduled at this time.
August 3, 2006 (PHOTOS opens in new window)
July 12, 2006 (PHOTOS opens in new window)
- THE INTAKE STRUCTURE - LADWP Construction forces have completed the
concrete floor of the lined channel and the 12’7” walls. The sloped channel is
complete. Construction crews have completed all shot-crete work.The rail car
bridge is scheduled to be installed by mid-July. The Langemann gate has
arrived and is installed.Scheduled work at the Intake is 95% complete with
remaining work to be completed as runoff activities cease.
- CHANNEL CLEARING - The initial two miles of river channel have been
cleared.Temporary access roads have been lightly disced and seeded to
facilitate revegetation, taking advantage of recent rains. These roads are
closed to vehicular traffic.
- CHANNEL OBSTRUCTIONS - Five of the six channel obstructions scheduled to
be removed for the LORP have been completed. The bridge foundation south of
Mazourka Cyn Road is in the process of being modified.
- BLACKROCK WATERFOWL AREA - Designated work is 50% complete.Work is
temporarily suspended due to runoff. Work will resume shortly as spreading
operations wind down, and will be completed prior to initial releases.
- MEASURING STATIONS - Measuring station near Blackrock ditch is complete
with the exception of placement of electronics. Electronics will be placed
just prior to initial flows. Reinhackle springs measuring station has began.
Work has temporarily been suspended due to runoff. Work will resume shortly as
spreading operations wind down, and will be completed prior to initial
releases.
- PUMP STATION - LADWP contractor Kiewit Pacific Co. has completed the slab
for the 50 cfs pump station sump floor and all walls. Structural backfill has
begun. False work installation is in progress for the top deck. First pour for
the top deck is scheduled for the week of July 20th. Excavation is complete
for the air chamber and approximately 50% of the protection slab and two of
the three main slabs have been poured. Air chamber walls are being formed. The
36” pipe is installed between the pump station and air chamber.The permanent
diversion structure earth work is complete. Sheet piling placement is
approximately 30% complete. Diversion structure floor and walls have been
placed. Top deck slab will be poured the week of July 20th which will complete
the concrete work for the diversion structure.Settling basin is
complete.Permanent service roads on the East and West sides are under
construction. Excavation and backfill are 70% complete.The Langemann gate has
arrived and is scheduled for installation during July.LADWP Intergrated
Support Services (ISS) crews began construction of the Industrial Station.
Underground conduits are installed and they are placing rock subgrade.
- POWER LINE - Power pole placement is in progress to provide power to the
pump station. Power will be on-site by mid September.BEAVER
- DAM REMOVALS - Beaver dams were removed in the Islands area July
5th. No future dam removals are scheduled at this time.
June 8, 2006 (PHOTOS opens in new window)
- THE INTAKE STRUCTURE LADWP Construction forces have completed the concrete
floor of the lined channel and the 12'7” walls. The sloped channel is 50%
complete and concrete pours will continue next week. Construction crews are
shot-creting the rear wall of the spillway and will have the wall completed by
June 10, 2006. The west bridge abutment has been poured and the forms
will be stripped Monday June 12 th . The east bridge abutment is being formed
and is scheduled to pour the week of June 12 th . The rail car bridge is
scheduled to be installed by mid-July. The Langemann gate has arrived and
installation will begin mid-June.
- CHANNEL CLEARING The initial two miles of river channel have been cleared.
Temporary access roads have been lightly disced and seeded to facilitate
revegetation, taking advantage of recent rains. These roads are closed to
vehicular traffic.
- CHANNEL OBSTRUCTIONS Five of the six channel obstructions scheduled to be
removed for the LORP have been completed. The bridge foundation south of
Mazourka Cyn Road is in the process of being modified.
- BLACKROCK WATERFOWL AREA Work is temporarily suspended due to runoff. Work
will resume shortly as spreading operations wind down, and will be completed
prior to initial releases.
- MEASURING STATIONS Preparation for the installation of the membrane is
complete work has temporarily been suspended due to runoff. Work will resume
shortly as spreading operations wind down, and will be completed prior to
initial releases.
- PUMP STATION LADWP contractor Kiewit Pacific Co. has completed the slab
for the 50 cfs pump station sump floor and all walls. Structural backfill had
begun. Excavation is complete for the air chamber and approximately 50% of the
protection slab and two of the three main slabs have been poured. Air chamber
walls are being formed. The permanent diversion structure earth work is
complete. Sheet piling placement is approximately 30% complete. Diversion
structure floor and walls have been placed. The concrete spillway weir is
scheduled for completion the week of June 12, 2006. Rip-rap placement for the
diversion structure has began. Settling basin is complete. Permanent service
roads on the East and West sides are under construction. Excavation and
backfill are 70% complete. The Langemann gate has arrived and is scheduled for
installation during July. LADWP Intergrated Support Services (ISS) crews will
begin construction of the Industrial Station the week of June 12, 2006.
- BEAVER DAM REMOVALS Three Beaver dams were removed in the Reinhackle
spring area May 23 rd and 24 th . No future dam removals are scheduled at this
time.